Monday 19 October 2026 to Friday 5 March 2027, 964 hours. Absorb is switched off on Friday 29 January 2027, with five weeks after it for the media studio, the tutor and buffer.
Design sign-off lands by 30 October, the end of week 2.
| Phase | Weeks | Ships | Hours |
|---|---|---|---|
| A. Design sign-off and foundations | 1 to 2 | Design signed off, Absorb export tested, the Laravel app with tenants, roles and SSO, Railway staging. | 110 |
| B. Course engine and Studio | 3 to 6 | Courses and versions, the board and outline, rules, the AI generator, the editors, the player, token wallets, the component runtime. | 212 |
| C. Assessment and learners | 7 to 9 | Question banks and exams, remediation, slide sessions, the learner portal, certificates. Staging release 18 Dec, payment 2 | 142 |
| D. Commerce, reporting, ILT, migration | 10 to 13 | Sessions and sign-off, reporting, Stripe, GST and Xero, the API and standards, branding, migration dry run. | 204 |
| E. UAT and cutover | 14 to 15 | UAT on migrated data, parallel run, completion record check, security and WCAG review, admin training. Absorb switched off 29 Jan, payment 3 | 68 |
| F. Media studio, tutor, polish | 16 to 20 | Hypercare, translation tracks, narration and video rendering, the media library, AI builds in the component studio, the tutor, buffer. | 228 |
| Total | 964 | ||
Test out per course. English first, then Hindi, Punjabi, Tamil, Tagalog and Mandarin. Licensed standards are uploaded by each tenant. Desktop and tablet for learners, desktop for admin. Regulatory data is always verified by a person, never AI. Markdown for all authors with design guardrails. No gamification.